HomeMy WebLinkAboutC.054.93009_1204Separate Prime: Plumbing Contract
P & H Plumbing 30,600 (low bid)
T.M. Caldwell Co. 35,540
Troutman Plumbing 33,700
Acorn Co. 35,721
Graham Plumbing 40,220
Separate Prime: Mechanical Contract
Griffin Co. 69,870
Wm. C. Reynolds Co. 94,138
Grahams Const. 76,570
Associated Cont. 70,918
Separate Prime: Electrical Contract
Lake Electrical 41,880 (low bid)
Fowler Electrical 53,500
Anderson Bros. 57,710
Watson Electrical 71,896
Progress Electrical 51,500
TOTAL MULTI PRIME $478,318
Single Prime: General Contract
White - Fox Builders 483,322
F & F Builders 548,273
Southern Constructors 505,896
Combined low bids for each of the separate prime contracts is a
total of $478,318, and is $5,004 less than the low single prime bid
of $483,322 including all contracts.
OTHER COSTS:
Telephone & Computer Installation $15,000
Architect Fee & Expenses 30,099
The low bids are recommended. The amount of $450,000 has been
budgeted. A budget amendaeat of $73,417 will be required if the
low bids are approved with a total cost of $523,417.
Goode mentioned that 10 ft. had been added to the building
length to accomodate office furnishings. Also, the mechanical
engineer stated that the tonnage for the air conditioning of the
building was not enough so this was increased. The General
Contract will have $5,000 in contingency.
Commissioner Madison asked for an opinion on the roof panel.
Goode said the standing seam roof was the best. The life
expectancy on the rib roof and standing seam roof are about the
same -- 20-25 years. The standing roof would have fewer leaks.
Commissioner Boone said that to comply with State laws the
price had increased. Goode said the project was under budgeted by
the General Contractor.
REQUEST FROM DOB FOR RENEWAL OF FOOD STAMP CONTRACT WITH
OFFICE WORLD$ Don Wall explained that Office World was awarded a
food stamp coupon issuance contract on April 18, 1995, at $.40 per
issuance. The contract can be renewed at the same price per
issuance.
Commissioner Johnson asked for the total price for this
service. Wall said that $46,000 had been budgeted last year, but
around $42,000 was the total cost. Wall said that his department
could not issue the food stamps any cheaper. If the DSS office
MAI? 375