Loading...
HomeMy WebLinkAboutC.054.93010_1154Vernon said the single -prime method was "cleaner." He said, "A general contractor could only go so far in multi -primes." Vernon said a multi -prime project was more difficult, even though it was less expensive. He said there was an $80,000 difference between the two methods for the project. Mashburn said the general contractor assumed more responsibility in a single - prime method. Commissioner Madison voiced concerns about wasting $80,000. Mashburn said the county could perform the project using the multi -prime method. He said the staff was recommending that (1) the awarding of the contract be delayed (2) permission be granted to obtain the design work for the lower level and (3) permission be given to negotiate with the low bidders about the additional work. UPDATE ON THE IREDELL COUNTY GOVERNMENT CENTER - SOUTH (ICGC-S) CHANGE ORDERS & CONTINGENCY ACCOUNT: Support Services Director Vernon said that when the ICGC-S architectural contract was approved, the board requested updates on the amount of contingency being used in the project. He said the contingency account had been depleted and $24,053 had been used from the Furniture/Fixtures/Equipment account. Vernon then described the following change orders and miscellaneous expenses. # Account Reason Amount G-1 Contingency Unknown existing $ 11,790 conditions G_2 Contingency Unknown existing 17,675 conditions G-3 Contingency Unknown existing 2,260 conditions G-4 Contingency Unknown existing 4,492 conditions G-5 Contingency Unknown existing 14,738 conditions G-6 Contingency Unknown existing 4,477 conditions G-7 Contingency & Unknown existing 15,852 Depreciable assets conditions G-8 Contingency Unknown existing 3,314 conditions _ G-9 General Fund Transfer Demolition of 3` /4 145,625 floors/DENR Total change orders $220,220 Total without DENR demolition = $74,595 Miscellaneous expenses (not part of construction contract) 1. Asbestos removal 0 floor for DENR project) 10,000 2. Mise. repairs to plumbing/HVAC piping not in contract scope of work (completed by Parlier Plumbing) 12,137 3. Asbestos removal completed prior to construction 67,600 4. Asbestos removal found during construction (contingency) 29,641 5. Roof repairs from contingency 6,605 Upcoming work to be done -- change orders not processed 1. Repairs to HVAC chiller/cooling tower 49,445 2. Change orders verbally approved 1,881 Vernon predicted the facility would be ready to open in mid-August. ADJ UChairman Johnson adjoume a briefing at 6:15 P.M. Approved: ` 6 ' za3 Ji' Clerk to the Board