HomeMy WebLinkAboutC.054.93010_1185 (2)Iredell County, North Carolina
Amended Capital Project Ordinance
ICGC-South - Phase 11- NCDENR Upfit
Be it Ordained by the Board of County Commissioners of Iredell County, North Carolina
Section 1.
This capital project fund shall finance the cost of planning, design, & renovations or
Be it Ordained by the Board of County Commissioners of Iredell County, North Carolina:
the space to be leased to NCDENR located in the ICGC-South.
Section 1. Funds for this Capital Project Fund will be provided from the following source:
Design, Renovation $ 1,604,375
Demolition 145 625
$.404 3QQ
Total $ 1.750.000
Section 2.
Funds for this Capital Project Fund will be provided from the following sources:
Transfer from Capital Reserve Fund
S 339,300
FY 02-03 $ 145,625
65,00
$: 4,04;3.4.0
FY 03-04 1,053,375
FY 04-05551>000
Manager
Total S-1 750.000
Section 3.
This Capital Project Fund shall continue until the project is complete.
Section 4.
Payments from this Capital Project Fund shall be authorized by the County Manager
or his designee.
Section 5. Upon completion of the construction project, all funds remaining in this Capital
Project Fund shall be transferred back to the Capital Reserve Fund.
This Ordinance being adopted July 15, 2003.
13. Request for Approval of the Following Three Items Pertaining to the Department of Social
Services Building Project:
Number 1
Capital Project Ordinance in the Amount of $404,300 for the Architectural Services
& Other Pre -Construction Costs as Estimated by MBAJ
Iredell County, North Carolina
Capital Project Ordinance
Department of Social Services Facility
Be it Ordained by the Board of County Commissioners of Iredell County, North Carolina:
Section 1. Funds for this Capital Project Fund will be provided from the following source:
Advance from Capital Reserve Fund
to be repaid upon receipt of financing proceeds
$.404 3QQ
Section 2. The following costs for the design and engineering of the Iredell County
Department of Social Services Facility shall be paid by this fund:
Basic A/E Fees & Consultants
S 339,300
Survey, Geotechnical, Testing, Reimbursibles
65,00
$: 4,04;3.4.0
Section 3. This Capital Project Fund shall continue until the project is complete.
Section 4. Payments from this Capital Project Fund shall be authorized by the County
Manager
or his designee.
This Project Ordinance being adopted July 15, 2003.
M